GALLERY: Week 57 progress (12 September 2016)

  • Further replacement of stone around the base of the tower is ongoing and will do so for the coming weeks.
  • The render for the new toilet amenities has been applied and is now ready for painting.
  • Waterproofing has been has been applied to the toilet amenities in preparation for tiling to occur next week.
  • The levee bank stair case walls have the applied finish, with the steps currently being formed up ready for concrete.
  • Set-out and establishment of pathways around the chapel is still ongoing. The proposed steps to the chapel/bell tower forecourt is in the process of being formed up ready for concrete.
  • The proposed landscape lighting is in the process of being installed.