GALLERY: Week 27 progress (15 February 2016)

  • The splayed buttress courses are currently being tooled and installed to the northern and southern facade, it is scheduled for these stones to completed next week.
  • All stone repairs and re-pointing will be completed on the Nave in the coming weeks, so that the scaffolding can be removed around the Nave on the week of the 7th March.
  • Australian Slate have now installed the copper downpipes to the gutters.
  • Protective measures have been applied to prevent smaller pieces of debris falling onto the completed slate roof.
  • The glass balustrade for Ancillary Building 'A' has been installed with the timber handrail now awaiting installation.

Week 27 progress