GALLERY: Week 54 progress (22 August 2016)

  • The bell tower parapet has now been completed and awaiting the four pinnacles to be installed.
  • Replacement of the stone and the repointing to the bell tower is ongoing.
  • The bell tower's large gothic window has had its leadlight glass reinstalled.
  • The installation of services for the toilet amenities have been completed, with the footings and slab to be poured later this week.
  • Garden beds and edging along with associated services have been installed in the Bishop's House backyard, in preparation for planting.
  • Site preparation and benching for the circular stairs which will connect the levee bank to the St John's Chapel gardens have commenced, with footings to be poured later this week.
  • Demolition of the existing timber floor structure of the proposed kitchen fitout has been removed, in preparation of the services to be installed.