GALLERY: Week 17 progress (7 December 2015)

  • The underlining to the raked ceiling of Ancillary Building 'A' will be completed early next week with the painter due to return on site to commence painting.
  • The high level stone on the southern side of the Nave, have been tooled onsite and is now in the process of being installed.
  • The required structural design solution to the western gable of the Nave has commenced. The works required involve a considerable amount of coring and anchoring to further stabilise the existing buttresses and parapet wall. It is proposed to be completed in January so that Australian Slate can finalise the install of the Welsh Slate roof.