GALLERY: Week 24 progress (25 January 2016)

The sill course for the northern and southern Nave, has now been installed along the entire length of the facade. Preparation of the upper level courses are being prepared.

Lyon Constructions have removed the timber formwork at the western gable end of the Nave in preparation for Australian Slate to return to complete the roof and flashing next week. The completed structural concrete beam will be encased in the copper flashing.

The painters have completed the first coat of paint to Ancillary Building 'A'.

Glass balustrade and tiling will commence early next week.

Week 24 progress