GALLERY: Week 9 progress (12 October 2015)

  • The new steel roof trusses and timber rafters are now in position.
  • The arrival of the slate and timber roofing battens are in place readiness for the roofers to commence early next week.
  • The proposed eastern gable end has required additional strengthening and is now in readiness for the stud wall and cedar cladding.
  • The steel work for the strengthening of the Bell Tower is in place and awaiting the steel rods to be chemically anchored into the sandstone walls.
  • The Bell Tower scaffolding will be completed and certified mid next week.
  • Towards the end of next week a 90 tonne crane will be onsite to remove the four pinnacles from the tower so that they can be further inspected.