GALLERY: Week 41 progress (23 May 2016)

  • Stone repair works around the eight bell tower/louvre windows are now complete and awaiting the install of the lourved windows.
  • JJJ course above the tower cornice has been delivered and installed as of 20/5/16.
  • Injected Westox damp proof course to the north and south nave is complete.
  • Cocoon poultice to the North and South nave was completed 14/5/16.
  • Renderer will be on site in four weeks time to commence the rendering of the North and South nave walls.
  • The copings to the North West and South West gables are currently being cut and fitted.
  • Pointing works to the tower are now approximately 75% complete.

Week 41 progress