GALLERY: Week 62 progress (17 October 2016)

  • Setout and establishment of pathways around the Chapel and Bishops House / Convent is still ongoing.
  • Central pathway which connects the circular staircase to the Chapels side doors has been formed and poured.
  • Inside the Chapel the floor is in the process of sanding and coating. This is a process over several stages.
  • Bishops House front yard has had the plants installed and new turf laid.
  • The steps which lead up to the Chapel from Cathedral Street, have now been formed and poured.

Week 62 progress