GALLERY: Week 60 progress (3 October 2016)

  • Stone mason is currently repairing minor flaws around the base of the bell tower.
  • Vanities and Toilet Partitions are currently being installed within the new toilet amenities building.
  • Tiling within the proposed commercial kitchen/servery area has now been completed, with painting to commence next week.
  • Setout and establishment of pathways around the Chapel and Bishop's House/Convent is still ongoing.
  • Turf and new plantings are currently being installed within the Bishops House/Convent.
  • Inside the Chapel ceiling and wall preparation has been completed with the painting.

Week 60 progress