GALLERY: Week 48 progress (11 July 2016)

  • The proposed landscape works have been approved by private certifier.
  • Site establishment has now commenced with the removal of existing vegetation along the levee bank.
  • The renderer has now applied the final application of render to the southern nave wall.
  • Preparation of the stone on the northern nave wall is taking place prior to the first application of the render.
  • Replacement of the stone on the bell tower buttresses is ongoing.