GALLERY: Week 6 progress (21 September 2015)

  • Redesign of the fixing plate for the new steel columns was required, due to the varying tolerances in the location of the steel beams within the existing concrete slab.
  • 70% of the nave sandstone has been ordered and is currently being worked offsite.
  • Removal of the existing concrete sill continued, in preparation for the new sandstone to continue up the wall to the underside of the eave.
  • Several days of wet weather hampered progress on the upper level.