GALLERY: Week 59 progress (30 September 2016)

  • Further replacement of stone around the base of the tower is ongoing and will do so for the coming weeks. Currently awaiting the arrival of the sandstone pinnacles before they are craned back into place.
  • Wall and floor tiling has been completed in the new toilet amenities and awaiting vanities and toilets to arrive.
  • All services have now been installed in the proposed commercial kitchen/servery area and all walls and ceilings are lined. Painting and tiling to commence next week, now that the waterproofing of the floors has been completed.
  • Setout and establishment of pathways around the Chapel and Bishop's House/Convent is still ongoing.
  • The internal restoration is proposed to commence next week.

Week 59 progress