GALLERY: Week 56 progress (5 September 2016)

  • The removal of the scaffolding around the bell tower has now been completed.
  • Further replacement of stone around the base of the tower is ongoing and will do so for the coming weeks.
  • The new toilet amenities roof, gutters and downpipes have been installed. The external brickwork also has been completed this week awaiting render to be applied.
  • Waterproofing and tiling to commence next week within the toilet amenities.
  • The levee bank stair case is currently having a render applied to the walls prior to a stone capping being installed which will follow the profile of the walls.
  • Setout and establishment of pathways around the chapel to commence next week.