GALLERY: Week 55 progress (29 August 2016)

  • The removal of the remaining scaffolding around the bell tower has commenced and is proposed to be brought down in 5-10 working days.
  • The timber wall and roof framing for the toilet amenities is close to completion, with the roof being installed next week.
  • The levee bank stair case has had the footings poured and is now currently forming the block walls to the appropriate heights. It is proposed to have the stair case established by the end of the week so the block work can be core filled. Stair landings to be benched and poured next week.

Week 55 progress