GALLERY: Week 37 progress (25 April 2016)

  • Bell tower cornice course of stone has been delivered and installed.
  • Pointing works to the tower are now approximately 60% complete.
  • The four bell tower pinnacles are a work in progress, in preparation of being installed.
  • Inspection of the bell tower's roof structure completed.