GALLERY: Week 28 progress (22 February 2016)

  • The splayed buttresses on the southern facade, require the upper splayed stone to be inserted for this facade to be completed of the install of high level stone replacement.
  • The larger splayed buttress stones are currently in place on the northern facade, with the upper splayed stone to be inserted for this facade to be also completed of the install of high level stone replacement.
  • The scaffolding is programmed to be removed from around the Nave on the week of the 7th March.
  • The Bell Tower stone is currently being prepared and marked for removal. Progress will increase on the tower once the high level works around the Nave have been completed.
  • A prototype has been manufactured for the replacement of the 8x louver windows located in the Bell Tower which are scheduled for replacement. Manufacturing of these windows will commence shortly.

Week 28 progress