GALLERY: Week 22 progress (11 January 2016)

  • The preparation of the sill course for the northern Nave is currently in progress.
  • Approval from the structural engineer has been given for the associated works to the western gable end of the Nave. Awaiting the return of Lyon Constructions for the formwork to be installed prior to the concrete pour.
  • Processing of the replacement stone in the bell tower in progress.
  • The removal of the cement render around the base of the nave is currently in progress. Once removed moisture readings will take place on a fortnightly occurrence.

Week 22 progress