GALLERY: Week 18 progress (14 December 2015)

  • The levelling course and the sub sill course on the southern side of the Nave, has been installed with the proposed sill and remaining full height courses currently being prepared. Over the holiday period the stonemason will carry out the same procedures on the northern side of the Nave. With the intent to complete these works throughout January and early February.
  • The required structural design solution to the western gable of the Nave is progressing and should be ready for the concrete pour mid January. These works required a considerable amount of coring and anchoring to further stabilise the existing buttresses and parapet wall.
  • The internal demolition of Ancillary Building 'A' has commenced for both levels in readiness for the internal fitout of the commercial kitchen and multipurpose meeting room.

Week 18 progress